| Part A - Systems Engineering for Digital Fabrication |
| 1 |
Digital Mock-Ups
Tall Buildings |
|
| 2 |
Tall Building Design
Tower Design Analysis |
Module 1: Analysis of existing tower design due |
| 3 |
Research Case - Design Production
Mock-Up - Control |
Module 1: Analysis of existing tower design due |
| 4 |
Materials and Assemblies |
Module 1: Material and manufacturing system analysis due |
| 5 |
Façade Design |
Module 1: Façade design due |
| 6 |
Façade Redesign |
Module 1: Façade redesign and packaging due |
| 7 |
Field Trip to NYC (Grimshaw and Sorkin) |
|
| Part B - Design Production |
| 8 |
Tower Design 1 |
Module 2: Tower production planning and review due |
| 9 |
Tower Design 2 |
Module 2: Tower production 1 due |
| 10 |
Tower Design 3 |
Module 2: Tower production 2 due |
| 11 |
Field Trip to London
Design Adjustment |
|
| 12 |
Redesign |
Module 3: Redesign due |
| 13 |
Final Presentation |
Module 3: Final review due |