ANDREW: Now we'll hear from
Chair Van Nostrand, who

00:00:14.120 --> 00:00:18.680 align:middle line:84%
has since, I believe, May
2023 chaired the Massachusetts

00:00:18.680 --> 00:00:20.670 align:middle line:90%
Department of Public Utilities.

00:00:20.670 --> 00:00:24.090 align:middle line:90%


00:00:24.090 --> 00:00:26.870 align:middle line:90%
JAMES VAN NOSTRAND: Thank you.

00:00:26.870 --> 00:00:28.241 align:middle line:90%
Thanks, everybody.

00:00:28.241 --> 00:00:30.830 align:middle line:90%


00:00:30.830 --> 00:00:33.980 align:middle line:84%
So I really appreciate the
opportunity to be here.

00:00:33.980 --> 00:00:36.020 align:middle line:84%
As Andrew mentioned,
I've been chair

00:00:36.020 --> 00:00:41.060 align:middle line:84%
of the commission coming up on
almost two years, May of 2023.

00:00:41.060 --> 00:00:42.650 align:middle line:84%
And one of the
things I inherited

00:00:42.650 --> 00:00:45.260 align:middle line:84%
was what was a pending
proceeding in Massachusetts

00:00:45.260 --> 00:00:47.750 align:middle line:84%
called the Future of
Gas Proceeding, where

00:00:47.750 --> 00:00:49.760 align:middle line:84%
we issued an order that's
very relevant to what

00:00:49.760 --> 00:00:51.300 align:middle line:90%
we've been talking about today.

00:00:51.300 --> 00:00:53.690 align:middle line:84%
I wanted to provide
a little bit of what

00:00:53.690 --> 00:00:55.160 align:middle line:90%
I had to learn when I got here.

00:00:55.160 --> 00:00:58.170 align:middle line:84%
I was a law professor in
West Virginia University.

00:00:58.170 --> 00:00:59.630 align:middle line:84%
You can imagine
kind of the culture

00:00:59.630 --> 00:01:03.930 align:middle line:84%
shock of going from a coal
state to a wonderful blue state

00:01:03.930 --> 00:01:06.600 align:middle line:84%
pursuing really aggressive
clean-energy targets.

00:01:06.600 --> 00:01:08.660 align:middle line:84%
But that provides the
framework for what

00:01:08.660 --> 00:01:11.510 align:middle line:84%
we're trying to do at the
Department of Public Utilities

00:01:11.510 --> 00:01:13.460 align:middle line:84%
and how network
geothermal potentially

00:01:13.460 --> 00:01:16.345 align:middle line:90%
fits into that whole message--

00:01:16.345 --> 00:01:17.220 align:middle line:90%
the whole initiative.

00:01:17.220 --> 00:01:19.080 align:middle line:84%
So what's the
statutory framework?

00:01:19.080 --> 00:01:19.922 align:middle line:90%
What are we doing?

00:01:19.922 --> 00:01:22.130 align:middle line:84%
And then a little bit about
the current demonstration

00:01:22.130 --> 00:01:24.110 align:middle line:84%
projects, but I think you've
probably heard a lot about those

00:01:24.110 --> 00:01:24.960 align:middle line:90%
already.

00:01:24.960 --> 00:01:27.230 align:middle line:84%
So one of the things is the
Global Warming Solutions

00:01:27.230 --> 00:01:30.870 align:middle line:84%
Act of 2008 said we're going
to be net zero by 2050,

00:01:30.870 --> 00:01:34.250 align:middle line:84%
and then later on, another
subsequent climate bill

00:01:34.250 --> 00:01:36.800 align:middle line:84%
says we're going to establish
sector-specific emissions

00:01:36.800 --> 00:01:39.930 align:middle line:84%
reduction targets
for 2025 and 2030.

00:01:39.930 --> 00:01:44.250 align:middle line:84%
So that was the Clean Energy and
Climate Plan of June of 2022.

00:01:44.250 --> 00:01:46.380 align:middle line:84%
And this is just an
excerpt from that plan,

00:01:46.380 --> 00:01:51.320 align:middle line:84%
but you can see starting off in
1990 and then to the far right

00:01:51.320 --> 00:01:53.940 align:middle line:90%
is 2030, four various sectors.

00:01:53.940 --> 00:01:55.620 align:middle line:84%
And you can see the
building sector.

00:01:55.620 --> 00:01:59.490 align:middle line:84%
You can see that reduction that
we need to achieve by 2030.

00:01:59.490 --> 00:02:04.580 align:middle line:84%
And this down below just
excerpts that building sector.

00:02:04.580 --> 00:02:07.120 align:middle line:84%
So that's what we're
striving for in terms of,

00:02:07.120 --> 00:02:09.070 align:middle line:84%
how does this network
geothermal fit into?

00:02:09.070 --> 00:02:11.890 align:middle line:84%
How does the transition to
the natural-gas industry, what

00:02:11.890 --> 00:02:13.250 align:middle line:90%
are we trying to accomplish?

00:02:13.250 --> 00:02:15.880 align:middle line:84%
It's really trying to
achieve those goals.

00:02:15.880 --> 00:02:18.370 align:middle line:84%
They're now statutory, the
Global Warming Solutions Act.

00:02:18.370 --> 00:02:21.920 align:middle line:84%
And the fact that the CESP, the
Clean Energy and Climate Plan,

00:02:21.920 --> 00:02:25.270 align:middle line:84%
established these subsector
targets pretty much

00:02:25.270 --> 00:02:29.120 align:middle line:84%
says residential's got to
get from 15.3 down to 7.8.

00:02:29.120 --> 00:02:31.310 align:middle line:84%
And for commercial and the
total percent reduction,

00:02:31.310 --> 00:02:33.230 align:middle line:90%
47% reduction.

00:02:33.230 --> 00:02:35.360 align:middle line:84%
And so that's what
we're trying to achieve.

00:02:35.360 --> 00:02:38.980 align:middle line:84%
That's basically I see
my job as a regulator is

00:02:38.980 --> 00:02:41.540 align:middle line:84%
these policy decisions have
been made by the legislature.

00:02:41.540 --> 00:02:46.600 align:middle line:84%
My job is to implement them
and try to make that happen.

00:02:46.600 --> 00:02:48.340 align:middle line:90%
So the statutory framework--

00:02:48.340 --> 00:02:51.440 align:middle line:84%
I think Ania talked about
this somewhat already,

00:02:51.440 --> 00:02:55.480 align:middle line:84%
but where network geothermal
comes into the 2021 climate

00:02:55.480 --> 00:02:59.650 align:middle line:84%
bill expressly allowed the
gas utilities to propose

00:02:59.650 --> 00:03:02.800 align:middle line:90%
these pilot-scale projects.

00:03:02.800 --> 00:03:05.870 align:middle line:84%
Another piece that came
in the following year--

00:03:05.870 --> 00:03:09.250 align:middle line:84%
and you may be hearing
a lot about GSEP,

00:03:09.250 --> 00:03:12.490 align:middle line:90%
or Gas System Enhancement Plans.

00:03:12.490 --> 00:03:14.320 align:middle line:84%
The gas utilities
in Massachusetts

00:03:14.320 --> 00:03:16.240 align:middle line:84%
are spending a lot
of money every year

00:03:16.240 --> 00:03:18.130 align:middle line:84%
to address what is
referred to in the statute

00:03:18.130 --> 00:03:19.760 align:middle line:90%
as leak-prone pipes.

00:03:19.760 --> 00:03:24.460 align:middle line:84%
So back in 2014, the Gas
Leaks Act was passed.

00:03:24.460 --> 00:03:28.150 align:middle line:84%
That basically provided
preferential rate recovery

00:03:28.150 --> 00:03:31.450 align:middle line:84%
for costs incurred
by the gas utilities

00:03:31.450 --> 00:03:34.250 align:middle line:84%
to repair or address
leak-prone pipe.

00:03:34.250 --> 00:03:37.040 align:middle line:84%
The notion is these
are safety issues.

00:03:37.040 --> 00:03:38.090 align:middle line:90%
They're risk issues.

00:03:38.090 --> 00:03:40.760 align:middle line:84%
Obviously, we have a lot of old
infrastructure in Massachusetts.

00:03:40.760 --> 00:03:45.610 align:middle line:84%
So that expedited rate recovery
sort of removes one of the tools

00:03:45.610 --> 00:03:49.990 align:middle line:84%
that we have as regulators,
which is called regulatory lag.

00:03:49.990 --> 00:03:52.240 align:middle line:84%
Typically a utility
will spend the money,

00:03:52.240 --> 00:03:55.330 align:middle line:84%
and then it won't recover
it in rates for a while.

00:03:55.330 --> 00:03:58.300 align:middle line:84%
Could be a year, two
years, but that gap

00:03:58.300 --> 00:04:01.000 align:middle line:84%
provides an incentive
for cost containment.

00:04:01.000 --> 00:04:03.360 align:middle line:84%
Well, what the Gas
Leaks Act did in 2014

00:04:03.360 --> 00:04:06.690 align:middle line:84%
was pretty much say we file
your gas system enhancement

00:04:06.690 --> 00:04:09.160 align:middle line:90%
plan with the DPU October 31.

00:04:09.160 --> 00:04:10.840 align:middle line:84%
We have six months
to go over it.

00:04:10.840 --> 00:04:14.740 align:middle line:84%
And then May 1, you begin
recovering those costs in rates.

00:04:14.740 --> 00:04:17.430 align:middle line:84%
So it provides this
expedited rate treatment

00:04:17.430 --> 00:04:21.660 align:middle line:90%
to address the leak-prone pipe.

00:04:21.660 --> 00:04:22.960 align:middle line:90%
So it's very controversial.

00:04:22.960 --> 00:04:26.370 align:middle line:84%
We had a GSEP working group
that met through a lot of 2023

00:04:26.370 --> 00:04:30.000 align:middle line:84%
to figure out that Gas Leaks
Act, having been passed

00:04:30.000 --> 00:04:34.265 align:middle line:84%
in 2014 focusing primarily on
the safety issue and the risk

00:04:34.265 --> 00:04:36.640 align:middle line:84%
issue, but then we have the
climate bill that says, well,

00:04:36.640 --> 00:04:38.890 align:middle line:84%
we need to achieve these
greenhouse-gas reductions.

00:04:38.890 --> 00:04:41.250 align:middle line:84%
Do we need to
revisit the Gas Leaks

00:04:41.250 --> 00:04:44.370 align:middle line:84%
Act in light of the
new focus on reducing

00:04:44.370 --> 00:04:45.700 align:middle line:90%
greenhouse-gas emissions?

00:04:45.700 --> 00:04:47.830 align:middle line:84%
And so a lot of work
is revisiting that.

00:04:47.830 --> 00:04:49.990 align:middle line:84%
We currently have those
filings in front of us.

00:04:49.990 --> 00:04:52.920 align:middle line:84%
We'll be issuing orders
April 30 with respect

00:04:52.920 --> 00:04:56.470 align:middle line:84%
to gas system enhancement
plans, beginning on May 1.

00:04:56.470 --> 00:04:59.370 align:middle line:84%
But a big thing in how network
geothermal fits into this

00:04:59.370 --> 00:05:00.785 align:middle line:90%
is the 2022 climate bill--

00:05:00.785 --> 00:05:02.410 align:middle line:84%
I think Ania might
have mentioned this,

00:05:02.410 --> 00:05:06.030 align:middle line:84%
but we can basically--
one means of addressing

00:05:06.030 --> 00:05:09.510 align:middle line:84%
the leak-prone pipe, rather than
just replacing it with more gas

00:05:09.510 --> 00:05:13.440 align:middle line:84%
pipe, is to replace it with
a utility-scale, nonemitting,

00:05:13.440 --> 00:05:16.560 align:middle line:84%
renewable thermal energy
infrastructure, a.k.a.

00:05:16.560 --> 00:05:18.070 align:middle line:90%
geothermal network.

00:05:18.070 --> 00:05:23.160 align:middle line:84%
So that is a big benefit
in terms of we're

00:05:23.160 --> 00:05:26.100 align:middle line:84%
trying to avoid potentially
stranded investment

00:05:26.100 --> 00:05:28.950 align:middle line:84%
by continuing to replace gas
pipes with gas pipes that are

00:05:28.950 --> 00:05:30.820 align:middle line:90%
going to last 50 or 60 years.

00:05:30.820 --> 00:05:34.170 align:middle line:84%
This says, well, when you're
spending that money on your GSEP

00:05:34.170 --> 00:05:38.160 align:middle line:84%
plan, you can actually use a
thermal energy network would

00:05:38.160 --> 00:05:40.830 align:middle line:84%
be one way of addressing
the leak-prone pipe

00:05:40.830 --> 00:05:44.100 align:middle line:84%
and avoiding that stranded cost
by just putting more natural-gas

00:05:44.100 --> 00:05:45.730 align:middle line:90%
infrastructure into the ground.

00:05:45.730 --> 00:05:50.430 align:middle line:84%
And as Ania mentioned, the
2024 climate bill actually

00:05:50.430 --> 00:05:52.530 align:middle line:84%
makes it specific
that a gas company

00:05:52.530 --> 00:05:55.650 align:middle line:84%
is allowed to get in
the business of creating

00:05:55.650 --> 00:05:57.720 align:middle line:90%
these thermal energy networks.

00:05:57.720 --> 00:06:00.740 align:middle line:84%
And then he also
mentioned we're trying

00:06:00.740 --> 00:06:02.360 align:middle line:84%
to address this
obligation to serve,

00:06:02.360 --> 00:06:03.960 align:middle line:90%
very controversial in the state.

00:06:03.960 --> 00:06:07.710 align:middle line:84%
But it's basically, as
you can see Ania's chart,

00:06:07.710 --> 00:06:12.882 align:middle line:84%
if you have a customer who does
not want to give up their gas,

00:06:12.882 --> 00:06:15.590 align:middle line:84%
how can you make the case, we're
going to substitute this network

00:06:15.590 --> 00:06:17.610 align:middle line:90%
geothermal for your gas?

00:06:17.610 --> 00:06:19.140 align:middle line:90%
Very controversial.

00:06:19.140 --> 00:06:21.710 align:middle line:84%
So they took a shot at
addressing the obligation

00:06:21.710 --> 00:06:25.350 align:middle line:84%
to serve, at least with
respect to new hookups,

00:06:25.350 --> 00:06:27.600 align:middle line:84%
by allowing the consideration
of adequate substitutes.

00:06:27.600 --> 00:06:29.810 align:middle line:84%
In other words, you might not
have a right to gas service

00:06:29.810 --> 00:06:31.260 align:middle line:84%
if there are
adequate substitutes,

00:06:31.260 --> 00:06:33.440 align:middle line:90%
the non-gas substitutes.

00:06:33.440 --> 00:06:36.440 align:middle line:84%
But we're still working
our way through this.

00:06:36.440 --> 00:06:39.170 align:middle line:84%
And then that eligible
infrastructure investment

00:06:39.170 --> 00:06:42.270 align:middle line:84%
in these GSEP programs,
it's not just replacement.

00:06:42.270 --> 00:06:44.090 align:middle line:84%
It also includes
retirement, which

00:06:44.090 --> 00:06:45.870 align:middle line:84%
means we can actually
take out the pipe.

00:06:45.870 --> 00:06:47.690 align:middle line:84%
One way of addressing
the leak-prone pipe

00:06:47.690 --> 00:06:49.320 align:middle line:84%
is just to remove
the leak-prone pipe

00:06:49.320 --> 00:06:50.730 align:middle line:90%
because you're going to convert.

00:06:50.730 --> 00:06:53.500 align:middle line:84%
You're going to convert
customers to electrification,

00:06:53.500 --> 00:06:56.000 align:middle line:84%
electrified solutions, whether
it's ground-source heat pumps

00:06:56.000 --> 00:06:58.550 align:middle line:90%
or air-source heat pumps.

00:06:58.550 --> 00:07:02.250 align:middle line:84%
So when I got here in May of
2023, I inherited this docket.

00:07:02.250 --> 00:07:05.310 align:middle line:84%
It had been started
in October of 2020,

00:07:05.310 --> 00:07:08.940 align:middle line:84%
and I think the record had
closed in October of 2022.

00:07:08.940 --> 00:07:10.940 align:middle line:84%
And I thought, I think
we need to probably issue

00:07:10.940 --> 00:07:15.800 align:middle line:84%
an order in this docket,
but it was basically,

00:07:15.800 --> 00:07:19.200 align:middle line:84%
what is going to be the pathway
for the natural-gas utilities?

00:07:19.200 --> 00:07:21.230 align:middle line:84%
How do we achieve these
greenhouse-gas reduction

00:07:21.230 --> 00:07:23.090 align:middle line:84%
targets, which the
Global Warming Solutions

00:07:23.090 --> 00:07:26.880 align:middle line:84%
Act and the 2021 climate
bill require us to achieve?

00:07:26.880 --> 00:07:30.110 align:middle line:84%
And so we issued this order
basically setting forth

00:07:30.110 --> 00:07:31.890 align:middle line:90%
this regulatory framework.

00:07:31.890 --> 00:07:34.310 align:middle line:84%
And what we basically landed
on was electrification

00:07:34.310 --> 00:07:36.450 align:middle line:84%
is going to be the
primary pathway,

00:07:36.450 --> 00:07:38.780 align:middle line:84%
and that's air-source heat
pumps, ground-source heat

00:07:38.780 --> 00:07:42.080 align:middle line:84%
pumps, which includes the
geothermal energy networks.

00:07:42.080 --> 00:07:44.870 align:middle line:84%
And the way I described what we
did in that order was basically

00:07:44.870 --> 00:07:49.070 align:middle line:84%
point out to this
clean-energy framework

00:07:49.070 --> 00:07:51.120 align:middle line:84%
that I had in the
first couple of slides.

00:07:51.120 --> 00:07:54.080 align:middle line:84%
We just want to put the LDCs,
the local gas distribution

00:07:54.080 --> 00:07:57.840 align:middle line:84%
utilities, on a pathway to
achieve net zero by 2050.

00:07:57.840 --> 00:08:03.170 align:middle line:84%
And so part of that is, in
a couple of months, April 1,

00:08:03.170 --> 00:08:06.710 align:middle line:84%
each LDC has to file a
climate compliance plan.

00:08:06.710 --> 00:08:08.260 align:middle line:84%
In other words,
show that you are

00:08:08.260 --> 00:08:11.090 align:middle line:84%
on a pathway that's going to
get you to net zero by 2050.

00:08:11.090 --> 00:08:13.210 align:middle line:84%
You're going to
achieve those sublimits

00:08:13.210 --> 00:08:14.930 align:middle line:90%
that I had on that other slide.

00:08:14.930 --> 00:08:17.080 align:middle line:84%
The other big thing
we did in 2080

00:08:17.080 --> 00:08:21.880 align:middle line:84%
was put the burden on the LDC,
the local gas distribution

00:08:21.880 --> 00:08:22.700 align:middle line:90%
companies.

00:08:22.700 --> 00:08:24.820 align:middle line:84%
Before you make any
additional investment

00:08:24.820 --> 00:08:26.690 align:middle line:84%
in natural-gas distribution
infrastructure,

00:08:26.690 --> 00:08:30.520 align:middle line:84%
show that you considered a
nongas pipeline alternative.

00:08:30.520 --> 00:08:32.809 align:middle line:84%
And that could be-- it
could be energy efficiency.

00:08:32.809 --> 00:08:35.260 align:middle line:84%
It could be air-source heat
pump, ground-source heat

00:08:35.260 --> 00:08:36.650 align:middle line:90%
pump, network geothermal.

00:08:36.650 --> 00:08:40.190 align:middle line:84%
But, basically, we want
to avoid stranded costs.

00:08:40.190 --> 00:08:42.860 align:middle line:84%
We want to avoid putting
additional pipe in the ground.

00:08:42.860 --> 00:08:44.690 align:middle line:90%
So that was a big element.

00:08:44.690 --> 00:08:47.290 align:middle line:84%
And right now, the natural-gas
distribution companies,

00:08:47.290 --> 00:08:48.620 align:middle line:90%
they're all working together.

00:08:48.620 --> 00:08:52.330 align:middle line:84%
They're going to be filing
with us an agreed-upon nongas

00:08:52.330 --> 00:08:55.010 align:middle line:84%
pipeline, an NPA
framework, because we

00:08:55.010 --> 00:08:57.010 align:middle line:84%
need to start applying
that as they're coming in

00:08:57.010 --> 00:08:59.710 align:middle line:84%
and asking for new,
additional investment.

00:08:59.710 --> 00:09:03.550 align:middle line:84%
Have you consider an NPA, that
Nongas Pipeline Alternative?

00:09:03.550 --> 00:09:06.440 align:middle line:84%
And then the other thing
that I think Ania mentioned,

00:09:06.440 --> 00:09:09.950 align:middle line:84%
so March 1, roughly
a year from now,

00:09:09.950 --> 00:09:13.710 align:middle line:84%
then we're requiring each LDC to
file a targeted electrification

00:09:13.710 --> 00:09:14.210 align:middle line:90%
project.

00:09:14.210 --> 00:09:16.660 align:middle line:84%
In other words, try to
take out/decommission

00:09:16.660 --> 00:09:19.540 align:middle line:84%
a portion of a gas
service territory in favor

00:09:19.540 --> 00:09:21.790 align:middle line:84%
of air-source heat
pump, ground-source heat

00:09:21.790 --> 00:09:25.122 align:middle line:84%
pump, electric, or
network geothermal.

00:09:25.122 --> 00:09:27.580 align:middle line:84%
You have to work with your
applicable electric distribution

00:09:27.580 --> 00:09:29.080 align:middle line:84%
company because in
Massachusetts, we

00:09:29.080 --> 00:09:31.610 align:middle line:84%
have some utilities that
are both gas and electric.

00:09:31.610 --> 00:09:34.510 align:middle line:84%
Sometimes Eversource
provides the electric

00:09:34.510 --> 00:09:36.320 align:middle line:84%
and National Grid
provides the gas.

00:09:36.320 --> 00:09:38.240 align:middle line:90%
You've got to come in together.

00:09:38.240 --> 00:09:40.540 align:middle line:84%
National Grid actually filed
a target electrification

00:09:40.540 --> 00:09:43.840 align:middle line:84%
demonstration proposal
in December of 2024

00:09:43.840 --> 00:09:46.050 align:middle line:84%
for the towns of
Leominster and Winthrop,

00:09:46.050 --> 00:09:47.800 align:middle line:84%
where they're going
to try to decommission

00:09:47.800 --> 00:09:49.175 align:middle line:84%
part of the gas
service territory

00:09:49.175 --> 00:09:51.290 align:middle line:90%
in favor of electrification.

00:09:51.290 --> 00:09:57.430 align:middle line:84%
But that's going to be a big
part of how we manage this gas

00:09:57.430 --> 00:10:00.600 align:middle line:84%
transition is the climate
compliance plans and the role

00:10:00.600 --> 00:10:04.480 align:middle line:84%
that these demonstration
projects are going to play.

00:10:04.480 --> 00:10:06.540 align:middle line:84%
And that's where the
obligation-to-serve piece

00:10:06.540 --> 00:10:08.850 align:middle line:84%
is so challenging because
when you look at the chart

00:10:08.850 --> 00:10:12.423 align:middle line:84%
that Ania had, all it takes
is one customer who says,

00:10:12.423 --> 00:10:14.340 align:middle line:84%
I don't want to give up
my gas, and you're not

00:10:14.340 --> 00:10:15.632 align:middle line:90%
able to take out that.

00:10:15.632 --> 00:10:17.340 align:middle line:84%
You're not able to
decommission the pipe,

00:10:17.340 --> 00:10:19.890 align:middle line:84%
and the numbers just don't
work all that well if you

00:10:19.890 --> 00:10:21.160 align:middle line:90%
can't decommission the pipe.

00:10:21.160 --> 00:10:23.460 align:middle line:84%
So that's why states
are struggling with,

00:10:23.460 --> 00:10:30.000 align:middle line:84%
how can we substitute
basically another means

00:10:30.000 --> 00:10:31.860 align:middle line:84%
of providing the
essential service of heat

00:10:31.860 --> 00:10:35.040 align:middle line:90%
instead of natural gas?

00:10:35.040 --> 00:10:39.540 align:middle line:84%
So one of the things that
it's helpful along the lines

00:10:39.540 --> 00:10:42.900 align:middle line:84%
of Ania's discussion of the
demonstration projects--

00:10:42.900 --> 00:10:45.240 align:middle line:84%
because the 2021 climate
bill specifically

00:10:45.240 --> 00:10:47.940 align:middle line:84%
authorizes the gas
companies to file with us

00:10:47.940 --> 00:10:51.540 align:middle line:84%
demonstration projects,
proposals, and it

00:10:51.540 --> 00:10:52.730 align:middle line:90%
lays out some criteria.

00:10:52.730 --> 00:10:54.730 align:middle line:84%
So when we look at these
demonstration projects,

00:10:54.730 --> 00:10:56.520 align:middle line:84%
when Framingham comes in
and when Eversource comes in

00:10:56.520 --> 00:10:58.830 align:middle line:84%
with the Framingham project
and National Grid comes in

00:10:58.830 --> 00:11:01.750 align:middle line:84%
for the Lowell and
Franklin Fields projects,

00:11:01.750 --> 00:11:03.210 align:middle line:84%
these are the
criteria that we are

00:11:03.210 --> 00:11:05.880 align:middle line:84%
going to apply in determining
the rate treatment, the rate

00:11:05.880 --> 00:11:09.300 align:middle line:90%
recovery of those costs.

00:11:09.300 --> 00:11:10.642 align:middle line:90%
Pretty straightforward.

00:11:10.642 --> 00:11:12.600 align:middle line:84%
Must have reasonable
likelihood of facilitating

00:11:12.600 --> 00:11:13.630 align:middle line:90%
substantial reductions.

00:11:13.630 --> 00:11:17.070 align:middle line:84%
That goes back to achieving
those greenhouse-gas limits.

00:11:17.070 --> 00:11:19.680 align:middle line:84%
We don't want you to
blend in hydrogen and RNG.

00:11:19.680 --> 00:11:22.120 align:middle line:84%
And we need to use a
third-party evaluation.

00:11:22.120 --> 00:11:24.810 align:middle line:84%
And then we consider
the reasonableness

00:11:24.810 --> 00:11:26.170 align:middle line:90%
of the size, scope, and scale.

00:11:26.170 --> 00:11:28.775 align:middle line:84%
In other words, do the benefits
justify the proposed cost?

00:11:28.775 --> 00:11:31.110 align:middle line:84%
And another key element
is the calculation

00:11:31.110 --> 00:11:32.970 align:middle line:84%
of benefits must
include the calculations

00:11:32.970 --> 00:11:35.340 align:middle line:84%
of the social value of
greenhouse-gas emissions

00:11:35.340 --> 00:11:35.860 align:middle line:90%
reduction.

00:11:35.860 --> 00:11:38.520 align:middle line:84%
That's going to be a
good way of, when you're

00:11:38.520 --> 00:11:40.067 align:middle line:84%
looking at those
costs and benefits,

00:11:40.067 --> 00:11:41.650 align:middle line:84%
you're going to put
a price on carbon,

00:11:41.650 --> 00:11:42.570 align:middle line:84%
basically, the
carbon that you're

00:11:42.570 --> 00:11:44.880 align:middle line:84%
avoiding by taking out that
natural-gas infrastructure

00:11:44.880 --> 00:11:47.350 align:middle line:84%
and replacing it
with something else.

00:11:47.350 --> 00:11:49.220 align:middle line:84%
So real briefly, I
think we're going

00:11:49.220 --> 00:11:50.970 align:middle line:84%
to hear a lot about
the Framingham project

00:11:50.970 --> 00:11:52.510 align:middle line:90%
that Eversource has done.

00:11:52.510 --> 00:11:55.707 align:middle line:84%
There's a phase II that was
awarded a preliminary grant,

00:11:55.707 --> 00:11:58.040 align:middle line:84%
I think, by the Department
of Energy, which is caught up

00:11:58.040 --> 00:12:02.000 align:middle line:84%
in all this stuff that's going
on in Washington, DC, right now.

00:12:02.000 --> 00:12:06.030 align:middle line:84%
So that was approved in the
Eversource rate case from 2020,

00:12:06.030 --> 00:12:07.700 align:middle line:90%
DPU 19-120.

00:12:07.700 --> 00:12:10.758 align:middle line:84%
And then National Grid had a
separate proceeding where--

00:12:10.758 --> 00:12:12.300 align:middle line:84%
this is before I
got here, of course,

00:12:12.300 --> 00:12:13.865 align:middle line:84%
but authorizing up
to $15.6 million

00:12:13.865 --> 00:12:17.270 align:middle line:84%
for four network geothermal
projects, the first of which

00:12:17.270 --> 00:12:18.240 align:middle line:90%
was in Lowell.

00:12:18.240 --> 00:12:20.450 align:middle line:84%
And I think National Grid
has announced that they

00:12:20.450 --> 00:12:22.460 align:middle line:90%
are terminating that project.

00:12:22.460 --> 00:12:25.560 align:middle line:84%
I think just the level of
participation wasn't as great.

00:12:25.560 --> 00:12:27.510 align:middle line:84%
The numbers didn't
work very well.

00:12:27.510 --> 00:12:29.990 align:middle line:84%
But they've also filed for
the Franklin Field Apartments

00:12:29.990 --> 00:12:31.530 align:middle line:84%
with the Boston
Housing Authority,

00:12:31.530 --> 00:12:34.345 align:middle line:84%
and so that project
is moving forward.

00:12:34.345 --> 00:12:35.970 align:middle line:84%
And then we'll be
looking-- like I say,

00:12:35.970 --> 00:12:37.260 align:middle line:84%
we'll be applying
those criteria.

00:12:37.260 --> 00:12:39.093 align:middle line:84%
Then we consider the
rate recovery treatment

00:12:39.093 --> 00:12:41.207 align:middle line:90%
of these demonstration projects.

00:12:41.207 --> 00:12:43.040 align:middle line:84%
So with that, I'm happy
to answer questions.