LEC # Topics Due Dates
1 Introduction

I. Strategic Connectivity
2 Information Technology, Corporate Strategy, and Competitive Advantage (Interlinked Value Chains)

3 Strategic Case Study (Johnson & Johnson Case) HW1: J&J
4 Business and Industry Transformation (McKesson Case)

5 Aggregators: Traveling the Internet “Fast Lane”

II. Physical Connectivity
6 Basic Communications Technology and Concepts CP1: Goals
7 Local Area Networks TP & CP Team Members
8 Wide Area Networks (Packet Networks)

9 Network Protocols (ISO OSI) CP2: LAN
10 Emerging Technologies I (Frame Relay, ATM, V-IP)

11 Emerging Technologies II (ADSL, Cable Modem) HW2
12 Technical Case Study - MIT’s Network Configuration TP Proposal/ CP3: WAN
III. Logical Connectivity
13 Distributed Homogeneous Databases

14 Mid-term Exam

15 Distributed Heterogeneous Databases HW3-A / CP4: DB Design
16 View Integration Among Databases

17 Web as a Database (COIN Project) CP5: View Integrate /ASP
18 Semantic Integration (COIN Project)

19 Component Architecture (CORBA) and Web Services

IV. Organizational Connectivity
20 Loosely-coupled Organizations CP6: Backend Integrate
21 Markets and Hierarchies: Organizational Coupling HW4
22 Development of Standards HW3-B
23 Motivating Strategic Alliances & Organizational Transformation Term Project / CP7: Final PAS
V. Finale
24 Course Summary and Review

25 Selected Student Presentations

26 Final Exam