KEY: SM - Stage Manager. TD - Technical Director.
| SES # | TOPICS | PERSONNEL | ASSIGNMENTS | NOTES | 
|---|---|---|---|---|
| 1 | Production Chosen | Director Designers Producer | Script to TA Academic Admin. for copying and distribution to Rinaldi staff. Rights to be procured. | |
| 2 | 22 Weeks to Opening 1st Design Meeting | Full Design Team: [Director, Scenic, Costume, Lights, Sound Designers, TD.] Producer, (SM, Props optional) | Director Presents: Concept and Thoughts on Scope of Design Elements | Include faculty advisors for Student designers. | 
| 3 | 20 Weeks to Opening 2nd Design Meeting | Full Design Team, Producer, (SM, Props optional) | Design Team Presents: Research | |
| 4 | 18 Weeks to Opening 3rd Design Meeting | Full Design Team, Producer, (SM, Props optional) | Design Team Presents: Rough Model | |
| 5 | 16 Weeks to Opening 4th Design Meeting - Presentation | Full Design Team, Producer, SM, Props, Crew Heads, Publicity | All Design Elements Presented and Finalized Scenic Painted Model (or) Costume Painted Sketches (or) Lighting Story Board/Sketches Sound Sound Plot | |
| 6 | 15 Weeks to opening | TD | Prepare Working Drawings and Detailed Budget | |
| 7 | 14 Weeks to Opening 1st Prod Meeting | Full Design Team, Producer, SM, Props, Crew Heads, Publicity [Production team] | Introduction Of Production Team Discuss Missing Personnel Directors Remarks on Production and Design Production Email List Discuss Detailed Production Schedule Production Hours Requirements Area Reports | |
| 8 | 14 Weeks to Opening | TD | Finish Working Drawings, Order Materials. | |
| 9 | 13 Weeks to Opening | Set Shop | Start Scenic Construction | Director and Production Stage Manager meet to discuss their working relationship and needs. A plan for auditions is created. | 
| 10 | 11 Weeks to Opening 2nd Prod Meeting | Production Team | Fill in Missing Personnel Area Reports | Production Stage Manager gets audition ‘sides’ from Director. | 
| 11 | 11 Weeks to Opening | Director, SM, Producer | Auditions for Production | Assistant Stage Manager is prepared to read with actors in auditions. | 
| 12 | 10 Weeks to Opening | Costume | Actors Measurements | |
| 13 | 10 Weeks to Opening | Producer | Distribute Contact Info for Cast and Crew | |
| 14 | 8 Weeks to Opening 3rd Prod Meeting text | Production Team | Review Schedule Put In Schedule Review Missing Personnel Area Reports | Two weeks before rehearsal meet with the actors and the stage managers. Assign the actors the difficult task of learning the “foreign language” over the school break. | 
| 15 | 4 Weeks to Opening | Director, SM, Actors | Start Rehearsals | Production Stage Manager begins taking rehearsal notes that are sent each evening after rehearsal. | 
| 16 | 4 Weeks to Opening | TD, Crew | Put in Set - If Possible | |
| 17 | 4 Weeks to Opening 4th Prod Meeting | Production Team | Area Reports Rehearsal Details | Actors go to costume shop to get rehearsal shoes comparable to the ones they will use in the play. Ditto-any gear necessary, i.e. eyeglasses, skirt, etc. These are to be used in rehearsal daily. | 
| 18 | 3 Weeks to Opening 5th Prod Meeting | Production Team | Area Reports Rehearsal Details | |
| 19 | 2 Weeks to Opening 6th Prod Meeting | Production Team | Area Reports Rehearsal Details | Stumble Through rehearsal in which the entire play gets knitted together. | 
| 20 | 2 Weeks to Opening | Lights, Crew | Hang Lights | Actors off book please. Italian Run Through, to reduce dead air, and make the actors think and react and act on their feet. | 
| 21 | 1 Week to Opening 7th Prod Meeting | Production Team | Area Reports Rehearsal Details Production Week | Stage Manager meets with Director, Lighting Design and Sound Designer to do a “Dry Tech” of the play. This is done over coffee, with scripts, and no actors. | 
| 22 | 6 Days before Opening | All Except Costumes | Q to Q | IAP Prod meeting after | 
| 23 | 5 Days before Opening | All Except Costumes | Tech | Prod meeting after | 
| 24 | 4 Days before Opening | All | Tech/Dress | Prod meeting after | 
| 25 | 3 Days before Opening | All | Dress | Prod meeting after | 
| 26 | 2 Days before Opening | All | Dress | Prod meeting after | 
| 27 | 1 Day before Opening | All | Final Dress Photos | Prod meeting after | 
| 28 | Opening | Enjoy | ||
| 29 | Performance Week 1 | Thu, Fri, Sat Performances Photo Call Sat After Performance | ||
| 30 | Performance Week 2 | Wed - Brush up Thu, Fri and Sat Performances Strike after Sat Peformance | 
 
		 
		 
		 
		 
		 
		 
		