KEY: SM - Stage Manager. TD - Technical Director.
SES # | TOPICS | PERSONNEL | ASSIGNMENTS | NOTES |
---|---|---|---|---|
1 | Production Chosen |
Director Designers Producer |
Script to TA Academic Admin. for copying and distribution to Rinaldi staff. Rights to be procured. | |
2 |
22 Weeks to Opening 1st Design Meeting |
Full Design Team: [Director, Scenic, Costume, Lights, Sound Designers, TD.] Producer, (SM, Props optional) |
Director Presents: Concept and Thoughts on Scope of Design Elements |
Include faculty advisors for Student designers. |
3 |
20 Weeks to Opening 2nd Design Meeting |
Full Design Team, Producer, (SM, Props optional) |
Design Team Presents: Research |
|
4 |
18 Weeks to Opening 3rd Design Meeting |
Full Design Team, Producer, (SM, Props optional) |
Design Team Presents: Rough Model |
|
5 |
16 Weeks to Opening 4th Design Meeting - Presentation |
Full Design Team, Producer, SM, Props, Crew Heads, Publicity |
All Design Elements Presented and Finalized Scenic Painted Model (or) Costume Painted Sketches (or) Lighting Story Board/Sketches Sound Sound Plot |
|
6 | 15 Weeks to opening | TD | Prepare Working Drawings and Detailed Budget | |
7 |
14 Weeks to Opening 1st Prod Meeting |
Full Design Team, Producer, SM, Props, Crew Heads, Publicity [Production team] |
Introduction Of Production Team Discuss Missing Personnel Directors Remarks on Production and Design Production Email List Discuss Detailed Production Schedule Production Hours Requirements Area Reports |
|
8 | 14 Weeks to Opening | TD | Finish Working Drawings, Order Materials. | |
9 | 13 Weeks to Opening | Set Shop | Start Scenic Construction | Director and Production Stage Manager meet to discuss their working relationship and needs. A plan for auditions is created. |
10 |
11 Weeks to Opening 2nd Prod Meeting |
Production Team |
Fill in Missing Personnel Area Reports |
Production Stage Manager gets audition ‘sides’ from Director. |
11 | 11 Weeks to Opening | Director, SM, Producer | Auditions for Production | Assistant Stage Manager is prepared to read with actors in auditions. |
12 | 10 Weeks to Opening | Costume | Actors Measurements | |
13 | 10 Weeks to Opening | Producer | Distribute Contact Info for Cast and Crew | |
14 |
8 Weeks to Opening 3rd Prod Meeting text |
Production Team |
Review Schedule Put In Schedule Review Missing Personnel Area Reports |
Two weeks before rehearsal meet with the actors and the stage managers. Assign the actors the difficult task of learning the “foreign language” over the school break. |
15 | 4 Weeks to Opening | Director, SM, Actors | Start Rehearsals | Production Stage Manager begins taking rehearsal notes that are sent each evening after rehearsal. |
16 | 4 Weeks to Opening | TD, Crew | Put in Set - If Possible | |
17 |
4 Weeks to Opening 4th Prod Meeting |
Production Team |
Area Reports Rehearsal Details |
Actors go to costume shop to get rehearsal shoes comparable to the ones they will use in the play. Ditto-any gear necessary, i.e. eyeglasses, skirt, etc. These are to be used in rehearsal daily. |
18 |
3 Weeks to Opening 5th Prod Meeting |
Production Team |
Area Reports Rehearsal Details |
|
19 |
2 Weeks to Opening 6th Prod Meeting |
Production Team |
Area Reports Rehearsal Details |
Stumble Through rehearsal in which the entire play gets knitted together. |
20 | 2 Weeks to Opening | Lights, Crew | Hang Lights |
Actors off book please. Italian Run Through, to reduce dead air, and make the actors think and react and act on their feet. |
21 |
1 Week to Opening 7th Prod Meeting |
Production Team |
Area Reports Rehearsal Details Production Week |
Stage Manager meets with Director, Lighting Design and Sound Designer to do a “Dry Tech” of the play. This is done over coffee, with scripts, and no actors. |
22 | 6 Days before Opening | All Except Costumes | Q to Q |
IAP Prod meeting after |
23 | 5 Days before Opening | All Except Costumes | Tech | Prod meeting after |
24 | 4 Days before Opening | All | Tech/Dress | Prod meeting after |
25 | 3 Days before Opening | All | Dress | Prod meeting after |
26 | 2 Days before Opening | All | Dress | Prod meeting after |
27 | 1 Day before Opening | All |
Final Dress Photos |
Prod meeting after |
28 | Opening | Enjoy | ||
29 | Performance Week 1 |
Thu, Fri, Sat Performances Photo Call Sat After Performance |
||
30 | Performance Week 2 |
Wed - Brush up Thu, Fri and Sat Performances Strike after Sat Peformance |